<article-title>PROBABILISTIC CALCULATION OF TOTAL<br/>
LABOR CONSUMPTION RATE OF REINFORCED<br/>
CONCRETE WORKS – WITH AND WITHOUT<br/>
CORRELATIONS</article-title>
</title-group>

<author>MARKUS KUMMER and CHRISTIAN HOFSTADLER</author>

<aff>Institute of Construction Management and Economics, Graz University of Technology,<br/>
Graz, Austria</aff>


</article-meta></front>
<body>
<abstract>
<title>ABSTRACT</title>
<p>Correlations between calculation parameters directly influence the results of
probabilistic calculations and their interpretation. In Monte Carlo simulations carried
out to systematically integrate uncertainties into the calculation process, input
parameter correlations are reflected by correlation coefficients and predominantly
influence the chance/risk ratio and ranges of results. Correlations are usually
determined indirectly by analyzing existing data series gathered from measurements,
surveys, experiments etc. and investigated with respect to their linear relationship.
Another option is to directly determine correlation coefficients based on expert
surveys. In 2015-16, Kummer and Hofstadler conducted a survey at Graz University of
Technology in which experts provided estimates of the coefficients corresponding to
the correlations between certain parameters. These considerations concentrated on the
labor intensity of reinforced concrete works expressed by the total labor consumption
rate, which indicates the amount of labor required for reinforced concrete works per
cubic meter of concrete. The total labor consumption rate of reinforced concrete works
must consider all activities carried out within the system, such as shuttering,
reinforcing and concreting. This paper presents and interprets survey results shown in
violin plots, and M-estimators are derived to deliver sound recommendations for
considering correlations when determining the total labor consumption rate of
reinforced concrete works. An example demonstrates the influence of input parameter
correlations on calculating the total labor consumption rate of reinforced concrete
works.</p>
<p><italic>Keywords: </italic>Monte Carlo simulation, Distribution function, Expert survey, Violin plot,
Chance/risk ratio, Histogram.</p>